Go To Search
Living in Orland ParkEnjoy Orland ParkBusiness and Development
How Do I? - Help Center
Online Services
Maycliff Subdivision - Update 11/10/15
Project Update
The contractor is continuing to install curb line inlets that outlet into the mainline storm sewers.  Additionally work on storm sewer within acquired easements is continuing.  All residents from which the Village is seeking an easement from have received easement documents and we are beginning to receive executed documents back.  The work on each remaining pipe run will begin as soon as all parties associated with that run have executed and returned the easement documents. 

Pavement patching and landscape restoration is currently underway on portions of the project that have been completed.  The project is anticipated to be substantially complete by Thanksgiving, pending the timely return and recording of the required easements. 

The sledding hill amenity added to Schuessler Park has had the split rail fence installed.  The seeding has begun to take with a fair amount of growth occurring.  Additional landscaping is being coordinated and will be installed prior to winter.  

The residents of the area will continue to see a number of construction vehicles, temporary road closures and impacts to traffic and access throughout the project limits during construction. 

Maycliff Stormwater and Watermain  


Project History

The Maycliff subdivision was started during the early 1960’s and continued construction of the infrastructure into the ’70’s.  Detaining storm water was only a concept at the time for the design of the subdivision.  The area streets hold water during major storm events and flooding occurs. 

The Village Board continues its efforts to reduce storm water drainage issues with the proposed storm water improvements to the Maycliff area. 

The proposed storm sewer system was designed by Christopher B. Burke Engineering LTD. (CBBEL) and will convey storm water from the residential area into the Schussler Park pond. Large diameter storm sewer pipe will be constructed north and south beneath 87th Avenue, eastward under 144th Street, south below 88th Avenue and discharge near the existing outlet to the Schussler Park pond. Smaller diameter sewers will be installed in various side and rear yards to help alleviate nuisance flooding. Airy’s, Inc. will be installing the storm water improvements.

The majority of the construction will take place within the village right-of-way, some work to install the necessary storm sewers and inlets will be required on private property at different locations. Once work begins, on street parking will be restricted for brief periods to allow for construction access. NO PARKING signs will be posted where needed. 

Water main improvements are also scheduled for construction this summer. A majority of the water mains within the subdivision will be lined, extending the life of the pipe and having less of an impact than traditional open cut construction.

The Village of Orland Park will be resurfacing or rehabilitating all streets within the subdivision in 2016.  

We appreciate your patience throughout this construction project. If you have questions or special concerns, please contact those listed below.

Travis Parry
Christopher B. Burke Engineering, Ltd
Project Engineer | 847.980.5315847.980.5315

Casey McCollom
Christopher B. Burke Engineering, Ltd
Resident Engineer | 847.833.7768847.833.7768

John Ingram
Village of Orland Park
Infrastructure Maintenance Director | 708.403.6350708.403.6350