Kristo Lane Stormwater Improvement
Project Update

The Kristo Lane stormwater project is completed with the exception of a few items.  Due to a watermain break, the final layer of asphalt has been delayed until the end of the season.


Background
The Kristo Lane study area is located south of 143rd Street and east of 82nd Avenue.  Preliminary design to determine the potential causes of the flooding and develop conceptual level alternatives to reduce or eliminate future flooding has been completed.  To expedite the construction of the project, the Village has elected to pursue the design-build delivery method for the Kristo Lane Stormwater Improvement Project.  The design build methodology allows construction of the project to begin while the design is being completed to save time and design costs.