Go To Search
Living in Orland ParkEnjoy Orland ParkBusiness and Development
How Do I? - Help Center
Online Services
Click to Home
Neighborhood Road Improvement Program - November 29, 2016

Project Areas

Project Status - Update November 29, 2016

The contractors for the village began in April, 2016.  The road improvement contractor chosen is D Construction. The areas for this year's neighborhood road improvements and there status are as follow:

Centennial Village - 
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work, pavement marking and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items. 

Doyle Court & 108th Avenue 
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items. 

Maycliff Estates -
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items.  

Kristo Lane / Dorstep Court -
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items.

Orland on the Green Unit 1 - North of 135th Street -
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items.


Orland on the Green Unit 2 - South of 135th Street -
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items. 

Ishnala Woods - 
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

During the next few weeks, the contractor will be completing deficiency list items.


Fernway - 167th Place and Robinhood Drive 
P.T. Ferro began work on this project on August 24.  All storm sewer culverts have been replaced, driveways restored, ditches graded, landscaping installed, curbs completed and the street has been reconstructed. 

This first section of the ditch/roadway improvement area of the Fernway subdivision is now complete.


Orlan Brook Drive Culvert Replacement 
Hasse Construction began work on this project the first week of September with the closure of Orlan Brook Drive beginning on Tuesday September 6.  All utilities, including water main have been relocated and the culvert pipes have been installed.  The roadway is open to traffic.  The contractor is now completed with all the work.


Asphalt Patching
Asphalt patching continues in various locations by the contractor.

Pavement Crack Sealing
The contractor, Patriot Pavement Maintenance is expected has begun work routing and filling cracks on asphalt pavement in various locations throughout the village.  Work is completed.

Shotcrete Curb Repairs
Work began by Ward & Associates for Shotcrete Curb Repairs at various locations within the village for the 2016 season.  Work is completed for the Village.

Sidewalk Gap Program
Construction of new walk at 88th Avenue and 135th Street will be completed during the week of November 28, 2016.

Sidewalk Slab Raising
Quick Raising Concrete began working in early April on various walks around Village owned properties.  Work is completed for this year.

Pavement Marking
Marking Specialists Corporation began pavement striping and marking for the 2016 season on May 25th.  The contractor is repainting lane striping and other pavement markings (stop bars, crosswalks) at various locations throughout the Village.  This work is completed.

Pavement Rejuvenators
American Road Maintenance applied GSB88 Pavement Rejuvenator June 28th on the pavement in Oland Woods and parts of the Preserves at Marley Creek.  Corrective Asphalt Materials applied Reclamite on portions of roadway pavement in the Preserves at Marley Creek .




Project Description
A street maintenance program is approved annually by the mayor and Board of Trustees. Various village-owned and accepted streets are scheduled for rehabilitation this year. The purpose of this program is to reconstruct streets which have deteriorated over and above normal maintenance.

Miscellaneous roadway patching will occur in areas throughout the village.

Inclusions
The program includes replacement of hazardous sidewalks, repair or replacement of non-functioning curbs and gutters, milling of the existing street, and new surface layer of asphalt.

This program does NOT include:
  • Replacement of driveways
  • Replacement of driveway aprons
  • Entry walks
  • Functioning curb and gutter meeting engineering standards

Please note: The above items are the responsibility of the homeowner.  Replacement cost is the responsibility of the homeowner. Remember that any driveway reconstruction / replacement requires a building permit.

Delays & Concerns
Street rehabilitation is unfortunately subject to weather conditions. Most materials and construction methods do not fair well in poor weather. Bad weather can therefore delay the project for a few days. We ask for your patience as we wait for better weather.

Most importantly, public safety is a primary concern for the village, contractor, and residents during the rehabilitation process. We ask that you please drive slowly and cautiously through the work areas. We realize that the project presents a significant inconvenience to many residents. Your patience during the construction process is greatly appreciated!


Street Surfacing Map
The Street Surfacing Map indicates the approximate year that the street was surfaced (completed) or resurfaced through the village's Neighborhood Road Improvement Program.