Go To Search
Living in Orland ParkEnjoy Orland ParkBusiness and Development
How Do I? - Help Center
Online Services
Neighborhood Road Improvement Program - July 27, 2016

Project Areas

Project Status - Update July 27, 2016

The contractors for the village began in April, 2016.  The road improvement contractor chosen is D Construction. The areas for this year's neighborhood road improvements and there status are as follow:

Centennial Village - 
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

Permanent pavement marking will be completed at the end of the project.


Doyle Court & 108th Avenue 
Contractors have completed all concrete sidewalk and curb removal & replacement, drainage improvements, paving work and landscape restoration.

Permanent pavement marking will be completed at the end of the project.


Maycliff Estates -
Contractors have completed all concrete removal & replacement and drainage improvements.  Also completed are the pavement removal, patching and the first layer of asphalt.

The contractor is working on completing sidewalk replacement this week.  Final layer of asphalt is scheduled to for this week.

Kristo Lane / Dorstep Court -
Contractors have completed all concrete removal & replacement and drainage improvements.  Also completed are the pavement removal, patching and the first layer of asphalt.

The final layer of asphalt has been delayed due to a water main break that occurred. The final layer of asphalt will be done at the end of the year.


Orland on the Green Unit 1 - North of 135th Street -
Contractors have completed all concrete removal & replacement and drainage improvements.  Also completed are the pavement removal, patching and the first layer of asphalt.
 
Contractors will continue with concrete Shotcrete repairs and placement of the final asphalt surface is scheduled for this week.


Orland on the Green Unit 2 - South of 135th Street -
Contractors have completed all concrete removal & replacement and drainage improvements.  Also completed are the pavement removal, patching and the top layer of asphalt.

Contractors will continue this week with concrete Shotcrete repairs.


Ishnala Woods - 
Contractors have completed all concrete curb and sidewalk removal & replacement and started on drainage improvements.  Also completed are the pavement removal, patching and the top layer of asphalt.

This week the contractor will be finishing the drainage repairs and begin the first layer of asphalt.


Fernway - 167th Place and Robinhood Drive 
No work has commenced in this area.

Southwest Highway at Brook Crossing Drive Intersection Improvement
No work has commenced in this area.

Orlan Brook Drive Culvert Replacement 
Hasse Construction has been awarded this project.  Work is expected to begin at the end of August.

There will be a four (4) week closure of Orlan Brook Drive tentatively scheduled to begin Tuesday, September 6, 2016.


Asphalt Patching
Asphalt patching continues in various locations by the contractor.

Pavement Crack Sealing
The contractor, Patriot Pavement Maintenance is expected has begun work routing and filling cracks on asphalt pavement in various locations throughout the village.  Work is expected to be completed this week depending on the weather.

Shotcrete Curb Repairs
Work began by Ward & Associates for Shotcrete Curb Repairs at various locations within the village for the 2016 season.  Work is expected to continue on various concrete repairs throughout the Village.

Sidewalk Slab Raising

Quick Raising Concrete began working in early April on various walks around Village owned properties.  Work is expected to continue at various locations on public sidewalk throughout the Village.

Pavement Marking
Marking Specialists Corporation began pavement striping and marking for the 2016 season on May 25th.  The contractor is repainting lane striping and other pavement markings (stop bars, crosswalks) at various locations throughout the Village.  This work is completed.

Pavement Rejuvenators
American Road Maintenance applied GSB88 Pavement Rejuvenator June 28th on the pavement in Oland Woods and parts of the Preserves at Marley Creek.  Corrective Asphalt Materials will be scheduling an application of Reclamite on untreated pavement in the Preserves at Marley Creek tentatively scheduled to begin in mid August.


Project Description
A street maintenance program is approved annually by the mayor and Board of Trustees. Various village-owned and accepted streets are scheduled for rehabilitation this year. The purpose of this program is to reconstruct streets which have deteriorated over and above normal maintenance.

Miscellaneous roadway patching will occur in areas throughout the village.

Inclusions
The program includes replacement of hazardous sidewalks, repair or replacement of non-functioning curbs and gutters, milling of the existing street, and new surface layer of asphalt.

This program does NOT include:
  • Replacement of driveways
  • Replacement of driveway aprons
  • Entry walks
  • Functioning curb and gutter meeting engineering standards

Please note: The above items are the responsibility of the homeowner.  Replacement cost is the responsibility of the homeowner. Remember that any driveway reconstruction / replacement requires a building permit.

Delays & Concerns
Street rehabilitation is unfortunately subject to weather conditions. Most materials and construction methods do not fair well in poor weather. Bad weather can therefore delay the project for a few days. We ask for your patience as we wait for better weather.

Most importantly, public safety is a primary concern for the village, contractor, and residents during the rehabilitation process. We ask that you please drive slowly and cautiously through the work areas. We realize that the project presents a significant inconvenience to many residents. Your patience during the construction process is greatly appreciated!


Street Surfacing Map
The Street Surfacing Map indicates the approximate year that the street was surfaced (completed) or resurfaced through the village's Neighborhood Road Improvement Program.